Reconstruction work of Sion Railway Flyover should be completed by July 15, 2026, directs Municipal Commissioner Ashwini Bhide

Published

on

Mumbai: Sewage Treatment Plant is very important in terms of environmental protection in the Mumbai Metropolitan Region, and care should be taken to ensure that the sewage treatment plant in Dharavi is functional by July 2027. The reconstruction of the Sine Railway Flyover connecting the eastern and western parts of Sine should be completed by July 15, 2026, while the road construction should be done as per the standard or standard. No new excavation should be done after April 30, 2026. The work of pouring concrete should be completed by May 15, 2026. In addition, Municipal Commissioner Smt. Ashwini Bhide has given various instructions that all road works should be completed by May 31, 2026 and the roads should be opened for traffic.

Municipal Commissioner Ashwini Bhide personally visited and inspected various development works in the city division today (April 16, 2026). These include a 418 million litres per day capacity sewage treatment plant in Dharavi, a flyover on the railway line in Shiv (Seon), cement concreting of roads in Shiv, protective measures taken by the Prajaniya Water Works Department to prevent rainwater from accumulating in the area of ​​Chuna Bhatti Railway Station, etc. During this, he gave various instructions. Additional Municipal Commissioner (Projects) Abhijit Bangar was present.

Dharavi Sewage Treatment Plant

The work of setting up a Sewage Treatment Plant (STP) with a capacity of 418 million litres per day in Dharavi by the Mumbai Sewage Project Department of the Mumbai Municipal Corporation is in full swing. Mrs. Bhide inspected the project. The physical progress of the Dharavi Sewage Treatment Plant project has reached 65%. The project is expected to be operational in July 2027. The project is based on Sequential Batching Reactor (SBR) technology. The project will be implemented in a multi-storey building on a very small footprint. A total of 7 sewage treatment plants are being built in the Mumbai Metropolitan Region and the sewage treatment plant in Dharavi is being built on the smallest footprint. Bhide inspected all the components of the project including the influent pumping station, sludge room, sequential batching reactor process tank, tertiary treatment building, sludge digester tank, shaft connected to the tunnel carrying sewage and shaft carrying treated water. The local difficulties faced in the completion of the project were reviewed and resolved. Mrs. Bhide directed to ensure that the Dharavi sewage treatment plant is operational by July 2027 in any case.

Sine Flyover
Municipal Commissioner Ashwini Bhide inspected the project site for the reconstruction of Sine Railway Flyover connecting the eastern and western parts of Shiv. During this inspection visit, the current status of the project work, remaining phases of the work and their timeframe were determined.
The work of installation of steel girders (girder launching) by the Railway Department is delayed by 15 days. As per the earlier plan, the girders were expected to be installed by April 30, 2026. Now this work has been postponed to May 15, 2026. Although the installation of the first beam has been postponed, Mrs. Bhide directed that this delay should be made up for in other ancillary works and the installation of both the beams should be ensured by May 20. Bhide also said that the Municipal Corporation Bridge Department and the Railway Department should coordinate with each other and ensure that all bridge works are completed by July 15, 2026.

Sign Road Cement Concreting Work

A total of 1,736 roads have been concretized till April 13, 2026 under Phase 1 and Phase 2 of the Mumbai Municipal Corporation’s major road cement concreting project, with a total length of 496.83 km. Under this, Mrs. Bhide inspected the road cement concreting works in Shiv of the city division. She inspected the main traffic section of Road No. 27 in Shiv East and the footpath work in Road No. 25 (C). Quality should be given priority while carrying out the concreting work. No excavation should be done after April 30, 2026. The concrete pouring work should be completed by May 15, 2026. At the same time, Bhide directed that all road work be completed and the roads be opened to traffic by May 31, 2026.

Maharashtra

Osama Bin Laden is reborn in Owaisi! Nitesh Rane once again strongly criticizes AIMIM leader Asaduddin Owaisi

Published

on

Mumbai: Maharashtra Minister Nitesh Rane once again criticized All India Majlis-e-Ittehadul Muslimeen chief Asaduddin Owaisi, who had earlier called him equal to Osama bin Laden, but now he said that Osama bin Laden has been reborn in Asaduddin Owaisi, and that is why he has such ideas. There is no place for those who reflect such ideas in India. He showed venom in the case of Nida Khan and said that AIMIM had supported Nida Khan, but now as the facts have been exposed, AIMIM has also been exposed. Nitesh Rane, while describing India as a Hindu nation, said that this is a country of gods and goddesses. If someone does not accept Vande Mataram, then he should take his beard and round cap and go to his father’s Pakistan because they will not be tolerated in India. He said that could these people support India while living in Pakistan? Only these people do such things while living in India. Even after comparing Owaisi to Osama bin Laden, Nitesh Rane is sticking to his stance, and Rane has even declared AIMIM a terrorist organization.

Continue Reading

Maharashtra

Instead of increasing parking fees by 40%, BMC should focus on affordable parking and traffic discipline, Raees Sheikh writes to Mumbai Municipal Commissioner

Published

on

Mumbai: As the Mumbai Municipal Corporation prepares to hike parking fees by 40 per cent, Samajwadi Party MLA from Bhiwandi East Raees Sheikh has written to Municipal Commissioner Ashwini Bhide, requesting him to review the current parking policy before increasing the fees and revive the defunct Mumbai Parking Authority (MPA). MLA Sheikh has demanded in the letter that the municipality should focus on improving traffic discipline and affordable parking instead of considering parking as a source of revenue generation. In his letter to the commissioner, MLA Raees Sheikh said that before making any changes in parking fees, a comprehensive review of the current parking policy and its implementation should be conducted. Citizens are facing many challenges due to inadequate parking infrastructure, uncontrolled parking on roads, lack of proper enforcement and irregularity of organized parking spaces. Before increasing parking fees, attention should be paid to making parking facilities affordable, transparent and accessible to the common citizen. MLA Raees Sheikh said that increasing fees without proper improvements in infrastructure and management can put unnecessary financial burden on residents, middle-class families, office workers and small traders. Stressing the need for strict enforcement of ‘no parking’ rules in the city, Raees Sheikh explained that traffic congestion due to illegal parking on roads, footpaths and squares is adding to the inconvenience of both pedestrians and motorists. Instead of just increasing parking fees, strict enforcement with better planning and digital monitoring system will help improve traffic discipline. The inefficient Mumbai Parking Authority should be revived so that parking management in the city is handled through a dedicated and accountable mechanism. MLA Raees Sheikh, in a letter to Commissioner Ashwini Bhide, suggested that a special authority could undertake scientific planning, formulate uniform parking policies, coordinate with the traffic police and transport departments and ensure a long-term solution to the growing number of vehicles in Mumbai.

Continue Reading

Maharashtra

Shocking Video! Man Gets Trapped Between Train & Platform At Andheri Station; Commuters Panic

Published

on

Mumbai: A disturbing video has surfaced from Andheri railway station showing a man trapped between a local train and the platform, triggering panic among commuters as bystanders rushed to rescue him.

According to a video shared by ‘Duniya Ke Khalesh’, the man was seen wedged in the narrow gap between the train and the platform. While the lower half of his body appeared to be under the train, his upper body and torso were stuck in the gap, with the man lying face-up as people gathered around in shock.

The visuals show the train standing still, indicating that the motorman had likely been alerted to the situation in time. Blood stains were also visible on the platform, reportedly after the man struck his head during the incident.

In the video, the man can be seen desperately attempting to pull himself free while commuters and railway staff cautiously try to rescue him without causing further injuries. Several people are seen coordinating efforts to slowly pull him out from the gap as panic spread across the platform.

No official statement regarding the incident or the condition of the man had been issued by authorities till the time of going to press.

This story comes to light a week after a man was spotted dead under a Mumbai local train, triggering panic and chaos among commuters at the station. The incident reportedly took place at around 12.05 pm.

According to a post shared by the ‘Mirabhyandarofficial’ page on Instagram, the man allegedly came under the local train at the station. Visuals from the spot show the lifeless body of the man under the train with only his legs visible. Visuals also show shocked commuters gathered around the platform.

Incidents like these once again highlight the dangers associated with crossing railway tracks or attempting risky acts near moving trains. Railway authorities have repeatedly urged commuters to remain cautious and follow safety rules while travelling on the suburban railway network.

Continue Reading
Advertisement
Advertisement

Trending