Connect with us
Wednesday,03-June-2026
Breaking News

Maharashtra

Mumbai Infra: Gargai Dam Proposal Cost Slashed After Review, BMC Saves ₹344 Crore

Published

on

Mumbai: After the standing committee raised concerns and returned the Gargai dam proposal, the contractor revised its bid from 9% to 1.9%. The civic authorities will now submit updated proposal, generating savings of Rs 269 crore on the base cost and Rs. 344 crore including taxes. The project, quoted at Rs. 3,276 crore, is now proposed at Rs. 3,065 crore, reducing the total cost including taxes from Rs. 5,396 crore to Rs. 5,051 crore.

The BMC initially estimated the Gargai dam project in Ogada village, Palghar district, at Rs. 3,006 crore. When tenders were invited in December, the lowest bidder, Soma Enterprises Ltd., quoted Rs. 3,334 crore, later reduced to Rs. 3,276 crore after a Rs. 57.73 crore concession—about 9% above the estimate, down from an initial 10.9%. However, the standing committee sought further cuts, the BMC held three more rounds of negotiations over the past two weeks, resulting the contractor to lower the cost further. 

The civic authorities will now submit the revised proposal to the standing committee for final approval. After the work order is issued, the project will still require clearances from the Central Wildlife Board and state and central forest departments. “The first year will focus on securing permissions and creating infrastructure to relocate six affected villages, followed by dam construction in the second year and installation of electrical systems in the third year,” said a senior civic official. The project includes a 1,200 kW hydropower unit to offset the dam’s electricity costs.

The Gargai Dam Project in Wada taluka, Palghar, aims to boost Mumbai’s water supply by 440 MLD. It involves constructing a 69‑metre-high dam near Ogada village and a 2.2 km tunnel to divert water to the Modak Sagar Reservoir. Implementation will require felling around 3.1 lakh trees, including areas within the Tansa Wildlife Sanctuary, necessitating compensatory afforestation on non-forest land. The project is expected to be completed by 2029.

The BMC supplies 4,000 MLD of water to Mumbai from seven lakes—Tansa, Bhatsa, Modak Sagar, Tulsi, Vihar, Upper Vaitarna, and Middle Vaitarna—but 34% is lost to theft and leakages. Rising pollution and urbanisation have pushed demand to 4,463 MLD, expected to reach 6,900 MLD by 2041. The last major dam, Middle Vaitarna, was completed in 2014. 

Maharashtra

Goregaon-Mulund Link Road Project: Work on connecting spare parts of tunnel boring machine to shaft for construction of twin tunnels under Phase 3-B is in full swing.

Published

on

Mumbai: The work of connecting the first tunnel boring machine is expected to be completed by the second week of June. Meanwhile, the work of connecting the second tunnel boring machine is in full swing in parallel. After the entire system of the first tunnel boring machine is installed at the project site, a Site Acceptance Test (SAT) will be conducted to check its performance, safety and proper functioning of all systems. This will mainly involve testing of mechanical, electrical, hydraulic, control and safety systems. After all the tests are found satisfactory as per the prescribed standards, the actual tunnel excavation will start.

Twin and underground tunnels will be constructed from Dadasaheb Phalke Chittarnagari in Goregaon to Khandipara in Malind. These twin tunnels, which are parallel to each other, are 4.70 km long each. The diameters of these parallel tunnels in the Sanjay Gandhi National Sanctuary area are 14.20 m and 13 m.
The excavation of both the tunnels has started as per the schedule and the target has been set to complete the excavation of the tunnels before October 2028. Overall, the Municipal Corporation is trying to complete the project by December 2028.

Continue Reading

Maharashtra

Deputy Mayor Sanjay Gadi visits drains in Kurla area, stresses on speedy completion of drain cleaning work before monsoon

Published

on

Mumbai: Deputy Mayor Sanjay Gadi today (June 3, 2026) inspected the ongoing drain cleaning work at Lokmanya Tilak Terminus Nallah, Nehru Nagar Nallah, Shivsarthi Nallah and Rahul Nagar Nallah in Kurla (East) area. Gadi said that various steps are being taken by the Municipal Corporation to increase the carrying capacity of the drains and ensure smooth drainage of rainwater in the backdrop of the monsoon season. During the inspection visit, local MLA Mangesh Kadalkar, Deputy Commissioner Zone 5 Scindia Nandedkar, Assistant Commissioner ‘L’ Division Dhanji Harlekar, besides concerned officers and employees were present. Deputy Mayor Gadi said that the drain cleaning work is going on as planned and the first phase of the work has been completed satisfactorily. Instructions have been given to regularly remove floating waste and sludge that often accumulates in the drains. The municipal administration is continuously working to clean the drains and maintain the flow of water. Necessary steps will be taken in collaboration with the railway administration, municipal administration and public representatives regarding the cleaning of drains in the railway limits. The work of cleaning the drains will be continuously monitored throughout the monsoon season and if the citizens face any problem, immediate action will be taken, Mr. Ghadi also clarified. During the inspection, the Deputy Mayor asked the concerned officers to remove silt and garbage from the drains in time, keep the water flow smooth and conduct additional cleaning drives at necessary places. Emphasis should be placed on keeping all the ‘manholes’ securely closed for the safety of the citizens.

Local MLA Mangesh Kadalkar said that continuous follow-up is being done in coordination with the administration to complete the work of cleaning the drains at the fastest pace.

Deputy Mayor Sanjay Gadde interacted with the local citizens and sought their suggestions and appealed to them not to throw garbage into the drains. He finally mentioned that it is important for the administration and citizens to make joint efforts to make Mumbai clean and water-free.

Continue Reading

Maharashtra

There will be 24 high waves in the sea during this monsoon, appeal to strictly follow the instructions given regarding high tides

Published

on

Mumbai will have 24 high tides during this monsoon, i.e., from June to September, during the 4 months. A high tide means that the sea will have waves of more than four and a half meters during this tide. It also mentions the date and time of the tide as well as the height of the waves rising in the sea. Accordingly, the highest waves in this monsoon will rise on July 16, 2026. The municipal administration has once again appealed to the citizens to avoid going near the beaches during high tide on all days and strictly follow the instructions issued by the Mumbai Municipal Corporation from time to time in this regard.
June 2026

  1. Sunday, 14.06.2026 AM – 11.24 AM Wave height (meters) – 4.65
  2. Monday, 15.06.2026 PM – 12.14 PM Wave height (meters) – 4.80
  3. Tuesday, 16.06.2026 PM – 01.05 PM Wave height (meters) – 4.87
  4. Wednesday, 17.06.2026 PM – 01.55 PM Wave height (meters) – 4.86
  5. Thursday, 16.06.2026 PM – 01.55 PM Wave height (meters) – 4.86 18.06.2026 PM – 02.44 Wave height (meters) – 4.79
  6. Friday, 19.06.2026 PM – 03.32 Wave height (meters) – 4.64

July 2026

  1. Monday, 13.07.2026 AM – 11.14 Wave height (meters) – 4.53
  2. Tuesday, 14.07.2026 PM – 12.04 Wave height (meters) – 4.73
  3. Wednesday, 15.07.2026 PM – 12.51 Wave height (meters) – 4.85
  4. Thursday, 16.07.2026 PM – 01.36 Wave height (meters) – 4.89
  5. Friday, 17.07.2026 PM – 02.19 Wave height (meters) – 4.83
  6. Saturday, 18.07.2026 PM – 03.00 Wave height (meters) – 4.66

August 2026

  1. Wednesday, 12.08.2026 AM – 11.48 Wave height (meters) – 4.68
  2. Thursday, 13.08.2026 PM – 12.28 Wave height (meters) – 4.81
  3. Friday, 14.08.2026 PM – 01.07 Wave height (meters) – 4.83
  4. Saturday, 15.08.2026 PM – 01.44 Wave height (meters) – 4.73
  5. Sunday, 16.08.2026 PM – 02.19 Wave height (meters) – 4.50

September 2026

  1. Thursday, 10.09.2026 AM – 11.26 AM Wave height (meters) – 4.57
  2. Friday, 11.09.2026 PM – 12.00 PM Wave height (meters) – 4.65
  3. Saturday, 12.09.2026 PM – 12.34 PM Wave height (meters) – 4.61
  4. Sunday, 13.09.2026 Midnight – 01.02 AM Wave height (meters) – 4.51
  5. Monday, 28.09.2026 Midnight – 00.38 AM Wave height (meters) – 4.51
  6. Tuesday, 29.09.2026 Midnight – 01.14 AM Wave height (meters) – 4.59
  7. Wednesday, 30.09.2026 Midnight – 01.53 AM Wave height (meters) – 4.56
Continue Reading
Advertisement
Advertisement

Trending