Business
Hundreds of crores spent in 23 years, yet NTPC Tandwa project’s future uncertain
Hundreds of crores have been spent in the last 23 years on setting up the National Thermal Power Corporation’s (NTPC) power plant at Tandwa in Jharkhand’s Chatra district, but till date no electricity has been generated from it.
Preparations were underway to start power generation from the first unit of the plant this month itself, but it seems unlikely due to a violent clash between the locals, whose properties were acquired for setting up the plant, and the police on March 7.
The agitated locals set ablaze 56 small and big vehicles deployed at the plant and vandalised the offices. A total of 27 people were injured from both sides in the clashes between the police and the agitating displaced people.
After the violent confrontation, the situation in the project and the surrounding areas are tense. The administration has imposed prohibitory orders in six villages affected by the project.
So far, seven people have been arrested in connection with the violence. Also, an FIR has been registered against 100 named and 800 unidentified persons.
Police are conducting flag marches in the areas around the project ever since the incident. However, 60 per cent of the staff are not coming to the office.
In such a situation, it is almost certain that the proposed trial of the first unit of the plant in March would be postponed.
The project, ever since its foundation stone was laid in 1999, has remained in disputes. People, whose properties were acquired for setting up the plant, have been holding protests for the last two decades raising demands such as financial compensation, rehabilitation and jobs.
On March 6, 1999, the then Prime Minister Atal Bihari Vajpayee had laid its foundation stone and people were hoping that a new chapter of development would begin in the area, which is infamous for Naxalism and backwardness. The target was to make the plant operational by 2002-2003.
Three units of the power plant are being installed here, aiming to produce 1,980 MW of electricity. And it was scheduled that the trial of the first unit, having the capacity of 660 MW, would commence in March 2022.
Equipped with modern technology, for the first time in the country, the thermal power plant is being established using the air-cooled condenser system technology that would bring down the water consumption to just 25 per cent.
With the completion of the project, apart from Jharkhand, electricity would also be supplied to Bihar, Odisha, Bengal and Northeast.
For the project, the land was mainly acquired from six villages and at that time the old law of land acquisition was in force.
Meanwhile, the government made a new law regarding land acquisition, wherein there is a provision that if the project for which the land has been acquired does not get started within five years, then the land will be returned to the farmers.
When the work of the project started after seven years due to delay in land acquisition and several other reasons, disputes erupted over compensation, rehabilitation, jobs to the affected. The work of the project continued to be affected due to dharnas, demonstrations, agitations.
In the last 23 years, there have been more than one hundred confrontations between the NTPC Management, Administration, Police and displaced persons. Also there were numerous incidents of firing, lathi charge and violence.
There were several agreements between NTPC, the administration and the villagers, but the dispute was never fully resolved.
In the meantime, compensation has been paid to most of the ryot or displaced persons. However, the project continued at a slow pace amid the regular interruptions.
About a year and a half ago, the dispute regarding the compensation for the acquired land erupted again. The organisation of the displaced locals started the agitation, saying the compensation received earlier was inadequate.
They intalled tents in front of the main gate of the NTPC project and have been continuously staging a sit-in for the last 14 months.
A senior official at NTPC says that the ryots from whom the land was acquired were given compensation in 2015 itself. “There is no such law that compensation should be given again for the same land. It’s just not possible.”
The agitating farmers have three main demands.
The first is that they should be paid compensation at the rate of Rs 20 lakh per acre and the ryots who have not been paid the compensation should be paid at the new rate along with interest.
The second demand is “each displaced family should be given a uniform rehabilitation package as presently the amount is being given to the people of different areas at different rates”.
Similarly their third demand is “Compensation in lieu of missing raiyati land, Gairmajarua Khas land, and houses, trees, ponds and wells situated on that land; 75 per cent grant to displaced ryots in NTPC-run schemes, and employment for every displaced family in NTPC”.
Business
Crude oil prices tank up to 20 pc over Iran ceasefire announcement

New Delhi, April 8: Global crude oil prices on Wednesday plunged sharply up to 20 per cent, after US President Donald Trump announced a two-week ceasefire with Iran that includes a pledge to restore navigation through the Strait of Hormuz — the narrow waterway at the heart of the world’s most acute energy crisis in decades.
The international benchmark Brent crude futures shed nearly 16 per cent or $17.39 to $91.88, hitting an intraday low, while US WTI crude declined almost 20 per cent or $21.90 to $91.05.
The Strait of Hormuz, through which roughly a fifth of global oil flows, has been at the centre of the conflict. Iran had restricted passage for several weeks, contributing to rising prices and supply concerns. Markets had been on edge ahead of Trump’s deadline for Iran to reach a deal, with traders fearing a major escalation could disrupt shipments across the Gulf and send prices sharply higher.
Oil prices had surged in recent weeks amid fears that the strait could be closed or severely restricted. The waterway handles shipments critical to global supply chains, including crude oil and liquefied natural gas.
The US-Israel-Iran conflict has been paused for two weeks after approximately 40 days of hostilities that began in February.
President Trump’s shift in stance came just ahead of his stated deadline for Iran to reopen the Strait of Hormuz or risk extensive strikes on its civilian infrastructure.
Meanwhile, Iran indicated it would halt its military operations provided attacks against it ceased simultaneously. Foreign Minister Abbas Araghchi, in a formal statement, confirmed that safe passage through the Strait of Hormuz would be ensured for two weeks in coordination with Iranian armed forces.
The conflict had triggered an unprecedented surge in oil prices in March, with gains exceeding 60 per cent during the period.
Additionally, Indian equity benchmarks also rallied sharply on the development, trading more than 3 per cent higher in early trade. The Sensex jumped nearly 4 per cent, while the Nifty surged 3.5 per cent to their respective intraday highs.
Business
Employees’ body to meet on April 13 as Central govt staff keen on 8th Pay Commission decisions

New Delhi, April 7: Millions of Central government employees and pensioners await the outcome of the drafting committee of the National Council (Joint Consultative Machinery) on April 13 to get cues on the 8th Pay Commission salary revision, a report said on Tuesday.
The drafting committee meeting scheduled for 11:00 am at the JP Choubey Memorial Library (AIRF office premises) here will review a final common memorandum and discuss pay scale revisions, annual increments, allowances and other benefits, the report from NDTV Profit said.
“The April 13 meeting is in continuation of the March 12, 2026, meeting when all drafting committee members of the 8th Pay Commission met to discuss the common memorandum of all employee and pensioner bodies,” said NC-JCM secretary, Shiv Gopal Mishra, in a letter to members of the drafting committee.
The government has not yet announced the official date for the salary increase. Arrears will be calculated based on the date fixed for the implementation of the 8th Pay Commission
even as employee and pensioner groups press for arrears to be calculated from January 1, 2026, the report said.
The Federation of National Postal Organisations has asked the government to merge the 58 per cent dearness allowance with basic pay and give interim relief from the same date.
The salary increase will hinge on the fitment factor the government adopts which analysts expect to exceed 2.5. Some employee groups have sought a fitment factor of 3.15, even though the official decision may take over a year, the report said.
Pankaj Chaudhary, MoS Finance, told Parliament in March that the 8th Pay Commission will make its recommendations on pay, allowances, pensions, and other benefits for central government employees. The 8th Pay Commission is expected to complete this work within 18 months from November 2025.
Business
Thane-Borivali Twin Tunnel Work Launched; Here’s How TBM Nayak Will Transform Travel For Mumbaikars

Mumbai: The first Tunnel Boring Machine (TBM), named Nayak, has been launched to begin excavation for the Thane–Borivali Twin Tunnel project today. The inauguration was officially done by Chief Minister Devendra Fadnavis along with Deputy Chief Ministers Eknath Shinde and Sunetra Pawar. Transport Minister Pratap Sarnaik was also present at the event, which took place at the TBM launch site in Manpada, Thane.
At present, the 23-kilometre journey between Thane and Borivali takes anywhere between 60 and 90 minutes, largely due to heavy congestion on Ghodbunder Road. Once completed, the new tunnel route will bring this travel time down to just 15 minutes, offering a faster and more reliable commute. The project, which began on May 19, 2023, is expected to be completed by May 2028.
Implemented by MMRDA, the project also includes connecting roads linking the Western Express Highway in Borivali and Ghodbunder Road in Thane.
A machine built for Mumbai’s toughest terrain, a 13.34-metre diameter single-shield TBM—among the largest deployed in urban tunnelling. Weighing nearly 2,500 tonnes and assembled from over a thousand components, the machine represents cutting-edge engineering tailored for challenging geological conditions.
Meanwhile, prior to this, Phase 1 of the long-awaited Metro Line 9 rail service between Dahisar East and Mira Bhayandar was inaugurated. CM Devendra Fadnavis, along with Deputy CM Eknath Shinde, Transport Minister Pratap Sarnaik, and Mumbai Mayor Ritu Tawde, were present at the inauguration ceremony of phase 1 connecting Dahisar East to Kashigaon.
The 4.97 km line connecting Dahisar and Kashigaon, with stations at Pandurang Wadi and Miragaon, is expected to provide relief to commuters in the Mira-Bhayander region, which currently depends heavily on road transport, leading to frequent traffic congestion.
-
Crime4 years agoClass 10 student jumps to death in Jaipur
-
Maharashtra2 years agoMumbai Local Train Update: Central Railway’s New Timetable Comes Into Effect; Check Full List Of Revised Timings & Stations
-
Maharashtra1 year agoMumbai To Go Toll-Free Tonight! Maharashtra Govt Announces Complete Toll Waiver For Light Motor Vehicles At All 5 Entry Points Of City
-
Maharashtra2 years agoFalse photo of Imtiaz Jaleel’s rally, exposing the fooling conspiracy
-
National News1 year agoMinistry of Railways rolls out Special Drive 4.0 with focus on digitisation, cleanliness, inclusiveness and grievance redressal
-
Maharashtra1 year agoMaharashtra Elections 2024: Mumbai Metro & BEST Services Extended Till Midnight On Voting Day
-
National News2 years agoJ&K: 4 Jawans Killed, 28 Injured After Bus Carrying BSF Personnel For Poll Duty Falls Into Gorge In Budgam; Terrifying Visuals Surface
-
Crime1 year agoBaba Siddique Murder: Mumbai Police Unable To Get Lawrence Bishnoi Custody Due To Home Ministry Order, Says Report
