The Bombay High Court granted bail on September 20, to Munib Iqbal Memon, one of the accused in the 2012 Pune serial blasts case, after he spent nearly 12 years in jail. Memon is required to furnish a personal bond of Rs 1 lakh, along with sureties of the same amount for his release, the report added.

A division bench comprising Justices Revati Mohite-Dere and Sharmila U. Deshmukh issued the verdict in response to Memon’s appeal, challenging a special court’s February decision that denied him bail. In September 2022, Justice Mohite-Dere had previously rejected Memon’s bail plea, citing a lack of reasonable grounds to believe he was not guilty of the charges.

The High Court has expedited the trial process, instructing the trial court to conclude proceedings by December 2023. Memon’s advocate, Mubin Solkar, argued that his client, a 42-year-old tailor, had been detained without trial for over 12 years, violating his right to a speedy trial, which warranted his release on bail.

The blasts occurred on August 1, 2012, on Pune’s Jangli Maharaj Road, injuring one person. An unexploded bomb was also defused at the scene. The Maharashtra Anti-Terrorism Squad (ATS) arrested Memon along with seven others for their alleged involvement in the incident. Memon faces multiple charges under various laws, including the Indian Penal Code (IPC), the Unlawful Activities Prevention Act (UAPA), the Maharashtra Control of Organised Crime Act (MCOCA), the Explosive Substances Act, and the Arms Act.

Maharashtra

Prakash Ambedkar’s VBA Announces 11 Candidates For Maharashtra Elections 2024; 1st List Includes Nagpur, Nanded, Aurangabad Seats

Published

on

Prakash Ambedkar's VBA Announces 11 Candidates For Maharashtra Elections 2024; 1st List Includes Nagpur, Nanded, Aurangabad Seats

Mumbai: As the Maha Vikas Aghadi (MVA) and Mahayuti alliances are busy with the rounds of meetings on seat-sharing and candidates finalisation, Vanchit Bahujan Aaghadi (VBA) on Saturday released its first list of candidates. The Prakash Ambedkar-led party included 11 candidates in its first list.

The elections for 288 state assemblies in Maharashtra will be held later this year. The polling schedule is yet not announced, but it is expected that voting will take place in mid-November with code of conduct coming into effect in next 15 days.

The 11 VBA candidates will contest in the constituencies of the cities like Chhatrapati Shambhajinagar, Nagpur and Nanded. The other seats includes Loha, Shevgaon, Raver, Sindhkhed, Khanapur, Dhamangaon Railway and Washim.

Prakash Ambedkar was supporting the MVA (Shiv Sena (UBT), NCP (SP), Congress) in Maharashtra during the recently concluded Lok Sabha elections. However, the seat-sharing talks failed and MVA decided to contest independently.

What Prakash Ambedkar Said

Announcing the first candidate list, VBA National President Prakash Ambedkar said, “Staying true to our sacred ideology, we have given representation to the deprived, Bahujan groups with the aim of gaining true representation and political power, and breaking the hegemony of families of certain castes.”

Transgender rights activist Shamibha Patil has been named the candidate for the Raver seat and Kisan Chavan, who belongs from the Pardhi community has been named from Shevgaon.

Ambedkar added that, “In the coming days, more names will be announced. We are in touch with very prominent political parties and soon more parties will join our alliance”.

“After failing to man-make the riots between OBC-Maratha, mainstream parties have resorted to the old and tested method of Hindu-Muslim divide. The silence of the mainstream parties should be questioned”, added Ambedkar.

Continue Reading

Maharashtra

Bale Shah Peer Dargah Illegal Construction PIL: Bombay HC Directs Trust, MBMC To File Para-Wise-Affidavit-In-Replies

Published

on

Mira-Bhayandar: The Bombay High Court on Friday directed the trustees and the Mira Bhayandar Municipal Corporation (MBMC) to submit affidavits in response to a civil public interest litigation (PIL) filed by Khush Khandelwal against an allegedly illegally constructed Dargah in the coastal area of Uttan near Bhayandar.

Direction Given To Dargah Trustees & The MBMC By Bombay HC

The bench of Chief Justice Devendra Kumar Upadhyay and Justice Amit Borkar directed the dargah trustees and the MBMC to file the affidavit-in-reply to the paragraph-wise averments made in the PIL within four and two weeks respectively. In legal terms, an averment is a statement of fact or allegation that is made in a charge, information, or in the pleadings of a civil claim.

Bombay HC Pulls Up MBMC

The HC also pulled up the MBMC for dragging its feet in acting against unauthorised constructions under the provisions of the Maharashtra Regional Town Planning (MRTP) Act. The counsel representing the trust submitted that at present no construction on the subject premises is being raised. 

Due to their absence in the previous hearing, the HC had directed fresh notices to be served to the trustees of the dargah (respondent number 6) while indicating that in case they are not represented in the next hearing, the matter may proceed ex-parte against it.

The petitioner-Khush Khandelwal who is the founder of the Hindu Task Force had filed the PIL (PILST/6843/2024) on 2, March 2024 alleging massive illegal constructions on land measuring more than 70,000 square feet by the Bale Shah Peer Charitable Trust on protected mangrove belts located on government-owned land parcels near the sensitive Chowk jetty in Uttan near Bhayandar.

Apart from facing allegations of illegal encroachments, the shrine is also under the scanner owing to concerns raised by security agencies following reports about alleged visits of people having shady backgrounds. However, the trust rubbishes the claims of shady visitors while continuing to maintain that the dargah has been in existence for more than two centuries ever since the saint Sayyed Bale Shah Peer came and stayed here. 

Continue Reading

Maharashtra

Mumbai: Dharavi Locals Halt BMC’s Attempt To Demolish Illegal Portion of Mosque, Trustees Request 4 Days

Published

on

Mumbai: Dharavi Locals Halt BMC’s Attempt To Demolish Illegal Portion of Mosque, Trustees Request 4 Days

Mumbai: Tensions flared in Dharavi, Mumbai’s largest slum area, on Saturday morning after a large number of local residents gathered to thwart the Brihanmumbai Municipal Corporation’s (BMC) planned demolition of an illegal section of a mosque. The mosque in question, Mehboob-E-Subhani Masjid, located on the 90 Feet Road, had been partially marked as an encroachment by the BMC, prompting civic authorities to issue an eviction notice for its removal.

The BMC’s team, arriving early at around 9 a.m. with the intent of pulling down the disputed portion of the mosque, was met with strong opposition from the local community. Hundreds of residents assembled on the road, physically obstructing the civic officials and preventing them from entering the narrow lane leading to the mosque.

Mosque Trustees Intervene

Amid growing tensions, local law enforcement quickly deployed a substantial number of personnel to prevent the situation from spiraling out of control. A police official confirmed the situation was under control, stating, “Heavy police ‘bandobast’ (security) has been deployed to ensure peace in the area.” Despite the massive gathering, no major incident of violence was reported, though the protest left authorities on high alert.

Following the impasse, residents escalated their protests by gathering outside Dharavi police station, demanding that the civic authorities halt the demolition process. Many residents were seen sitting on the road in protest, voicing their concerns over what they believed to be an unfair move against the mosque.

As tensions mounted, the mosque’s trustees intervened by appealing to the BMC for more time to address the issue themselves. In a written request submitted to the Deputy Commissioner of Circle 2 and the Assistant Commissioner of G-North Division, the trustees requested four to five days to voluntarily dismantle the encroached portion of the mosque. They assured the authorities that they would remove the illegal construction without the need for civic action.

BMC Issues Statement

In an official statement, the BMC acknowledged the trustees’ request, stating: “The trustees have sought four to five days to remove the encroached portion of the mosque on 90 Feet Road on their own.” The municipal body also confirmed that it had accepted the trustees’ proposal, providing them with the requested extension to complete the task.

The dispute centers around a notice issued by the BMC to the mosque’s management, ordering the removal of an encroached structure that had allegedly been built on public land. The Mehboob-E-Subhani Masjid, located along a busy stretch of Dharavi’s 90 Feet Road, had reportedly extended part of its construction beyond its legal limits, leading to the BMC’s decision to take action against it.

The municipal administration explained that the notice was issued in accordance with legal procedures and that appropriate action was being taken in response to the violation. A BMC official said, “The trustees have been instructed to remove the illegal portion within the stipulated time, and the BMC will ensure that the encroached construction is removed as agreed.”

While the trustees’ agreement to voluntarily dismantle the structure has temporarily calmed the situation, residents remain uneasy. Many argue that the mosque is a key religious and community landmark in the area, and any action taken against it could disrupt the delicate social fabric of the slum, which houses people of various faiths.

One local resident, who participated in the protest, said, “The mosque has been here for a long time, and it is an important part of our community. The authorities need to find a more balanced solution rather than resorting to demolition.”

However, others, including civic authorities, have pointed out that illegal encroachments contribute to overcrowding, traffic bottlenecks, and a lack of infrastructure development in the already congested Dharavi area.

The BMC has clarified that while the trustees’ request for additional time was granted, the removal of the encroached portion must be completed within the agreed-upon timeframe. Should the trustees fail to fulfill their commitment, the BMC will take further action to demolish the structure as per the original notice.

With the deadline approaching, local authorities are keeping a close watch on the developments. Police officials have reassured the public that security will remain in place to prevent any escalation of tensions. Civic officials, meanwhile, have expressed hope that the matter will be resolved peacefully and in accordance with the law.