General
Mumbai News: Ram Karan Yadav Takes Over As General Manager Of Central Railway
Ram Karan Yadav has taken over as the new General Manager of Central Railway on 01st December 2023.
He is a senior officer of the Indian Railways Service of Engineers (IRSE) of 1986 exam batch. Before taking over as General Manager, Central Railway, he was working as Director General, Indian Railways Institute Of Civil Engineering (IRICEN), Pune. He succeeds Naresh Lalwani.
About Yadav’s Academic Background
Yadav did his BE (Civil) with Honors from IIT Roorkee in 1985 and received Uttar Pradesh P.W.D. Centenary Gold Medal and University Silver Medal for standing first in Transportation Engineering. He did his M.Tech (Soil Mechanics & Foundation Engineering) from IIT Delhi in 1987. He joined Railways in March 1988. He has a very rich and vast experience of having worked on Infrastructure projects. He has served on various posts in field as well as in Hd.Qrs. on Western Railway, North Eastern Railway, Central Railway, Eastern Railway, IRICEN Pune, RITES and Delhi Metro Rail Corporation.
During his tenure as Director General, IRICEN, Pune he was involved in Organising and planning training for officers of Civil Engineering, Preparation of Question papers promotion to Group B, Revision of Codes and Manuals of Civil Engineering.
Yadav’s Career Background
As Chief Administrative Officer (Construction) on Western Railway, highest ever commissioning of New Line, Gauge Conversion and doubling on WR in a year was done. Six projects of Gauge Conversion and Doubling which were pending since long time were completed. Work of 6th line between Khar and Borivali on Western Rly Mumbai suburban also picked up pace during his tenure. Work on major Station Development of Udhna, Sabarmati and Bhuj also commenced.
As Chief administrative Officer (Construction) on North Eastern Railway he has Commissioned 245 RKM of Railway Electrification, 53 km of Doubling with Electrification and 42 km of Gauge Conversion. Out of this 125 RKM of Electrification was commissioned in one go which is the highest ever achievement by any construction unit of Indian Railways. After critical review of various ongoing projects of Doubling and Gauge Conversion a saving of more than Rs 350 Cr was achieved.
As Chief Project Director (Station Development) on Central Railway he was involved in development and approval of plan of Inter Modal Station at Ajni, Nagpur, Integration of station with Metro station at Ghatkopar, Remodelling of Thane, Kalyan and CSMT Mumbai Stations and monetisation of Railway land at Matunga station.
While working as Divisional Railway Manager, Bhusawal led a multidisciplinary team of more than 17000 staff. Apart from overall improvements in infrastructure and operational parameters he has taken removal of encroachments from Railway land as a mission and succeeded in removal of 80% of the encroachments from Railway land on the division. In one of the biggest drive of removal of encroachments on Indian Railways carried out from 15th to 17th Nov 2018, more than 3000 houses (hutment/Pucca houses) and approximately 350 shops were removed from Railway’s land at Bhusawal and more than 120 acres of precious land was reclaimed. In March, 2019 he received Leadership & Performance Excellence award from Minister of Railways for providing strong leadership and performance excellence directed towards improving delivery on Indian Railways as Divisional Railway Manager, Bhusawal.
While working as head of the Property Business Department of Delhi Metro Rail Corporation (DMRC) total earning of Property Business Cell increased from Rs 158.88 Cr (during year 2014-15) to Rs 230.78 Cr (during year 2016-17) i.e. 45% increase. Earning (NFR) of Airport Line increased from Rs 10.27 Cr (during year 2014-15) to Rs 40 Cr (during year 2016-17), thus taking out operationally loss making Airport Metro Line to operationally profit making line.
He has also worked as Chief Engineer (Construction) on Eastern Railway and executed New Line and Doubling works. As GM/Urban Transport/RITES Mumbai he has carried out feasibility study of Elevated Corridor along Western Railway sub-urban routes. He has worked as Independent Safety Officer in execution of Mumbai Metro One.
At IRICEN Pune as Senior faculty he has conducted various courses on Contract and Arbitration at Institute as well as on various zonal Railways. He was also involved in organising training courses for civil engineers of Indian Railways; delivering lectures on various subjects like Long Welded Rails, Curves, Track Maintenance, Rehabilitation of Bridges, Mechanised Track Maintenance, Contract & Arbitration; writing articles and editing articles for IRICEN Journal and organizing and conducting track seminar for Chief Track Engineers of Indian Railways.
Yadav’s Achievements
He has received General Manager’s award in 1999 for excellent planning and execution of 12m wide foot over bridge (FOB) with PSC girders at Dadar Station which is the widest FOB on Railway system. Also during his tenure as Senior Divisional Engineer (Co-ord.), Pune Division has received Engineering Efficiency Shield of Central Railway in 2004 for excellent planning and execution of Engineering Works on the division.
He has attended Executive Leadership Program (for DRMs) at SDA Bocconi School of Management, Milan, Italy and Advance Management Training Program at INSEAD Singapore and ICLIF, Malaysia. He has also attended Strategic Management Work shop at ISB Hyderabad and Leadership Enhancement Development Program at ISB Mohali.
Maharashtra
Municipal Commissioner directed to complete work on Bhandup Water Purification Project to ensure safe water supply to Mumbai

The state-of-the-art 2,000 million litres per day (MLPD) water treatment plant to be set up at the Bhandup Complex will significantly enhance the efficiency, transparency and resilience of the Mumbai Metropolitan Region’s water supply system. The project will help Mumbaikars get better quality, safe and sustainable drinking water as per national and international standards. Considering the growing population of the Mumbai Metropolitan Region, the pace of urbanisation, the growth of the industrial and commercial sector, as well as the increasing demand for water in the future, it is a key infrastructure project for Mumbai’s long-term water security. Municipal Commissioner Ashwini Bhide has directed that all necessary steps be taken to expedite all civil, structural, electrical, mechanical and process engineering works related to this water treatment project and complete the project ahead of schedule. A state-of-the-art Water Treatment Plant (WTP) with a capacity of 2,000 million litres per day (MLD) is being set up by the Mumbai Municipal Corporation (BMC) at Bhandup Complex. The water treatment project is expected to be completed by July 2028. Municipal Commissioner Ashwini Bhide visited the site of the water treatment project today (June 17, 2026) and inspected it. He also reviewed the progress.
Additional Municipal Commissioner (Project) Abhijit Bangar, Deputy Commissioner (Municipal Commissioner’s Office) Prashant Gaikwad, Deputy Commissioner (Special Engineering) Parshottam Malwade, Deputy Commissioner (Engineering) Shri. Shashank Bhoor, Chief Engineer (Water Supply Project) Chandrakant Choudhary, Chief Engineer (Mumbai Sewerage Project) Ashok Mengade, Chief Engineer (Bridges) Rajesh Mulla along with concerned engineers and officers were present on the occasion. There are two main systems for supplying water to Mumbai. From one of them, through the Tansa-Vitarna system, water from Tansa, Modak Sagar, Madhya Vitrna and Upper Vitrna dams is brought to the Bhandup Complex by gravity through water channels. This water is purified at the water purification centre in the Bhandup Complex. About 2500 million litres of water is supplied to the people of Mumbai daily through water reservoirs located at various locations. The 1910 million litres per day water purification project in the Bhandup Complex was built about 43 years ago. As the project has become structurally weak, a new water treatment project is being set up with a capacity of 2,000 million litres per day (MLD). The new water treatment project will process 2,000 million litres per day (MLD) of water. This water treatment project is crucial to increasing the capacity of the Bhandup Complex, which supplies water to the western and eastern suburbs of Mumbai.
Municipal Commissioner Ashwini Bhide said that the new water treatment project on 7.4 hectares of land in the Bhandup Complex will replace the existing project, which is the largest in Asia. It will help provide clean water to Mumbai. Its main objective is to meet the growing demand for water and replace the old project, which has reached the end of its life. Currently, soil testing, excavation, site clearance, relocation of power lines, tree planting, etc. are in full swing. Along with the construction works, mechanical, electrical and instrumentation work has also been started in parallel. The project works should be completed expeditiously by making additional manpower and machinery available. Instructions have been given to plan for excavation, radar transportation. Overall, the Brihanmumbai Municipal Corporation is committed to bridging the gap between the demand and supply of water for Mumbaikars. Bhandup Sewage Treatment Plant to be functional by October 2026.
The work of the 215 million litres per day (MLD) capacity sewage treatment plant project in Bhandup is in the final stages. Municipal Commissioner Ashwini Bhide inspected the work today (June 17, 2026). Bhide directed that the project be fully implemented by October 2026.
In view of environmental protection in Mumbai, the Brihanmumbai Municipal Corporation is setting up sewage treatment plants at a total of 7 locations. Under this, the work of Sewage Treatment Plant project is underway in Bhandup. Under this, the construction work of Primary Treatment Unit, Primary Clarifier, Continuous Sequencing Batch Reactor Tank, Air Blower Building and Digesters etc. has been completed. Mrs. Bhide inspected all the works and took detailed information.
Municipal Commissioner Ashwini Bhide said that the state-of-the-art Sewage Treatment Plant with a capacity of 215 million litres per day in Bhandup will be an important milestone for the Mumbai Metropolitan Region.
Maharashtra
Eknath Shinde’s Operation Tiger was successful… Uddhav Thackeray’s rebellion in Shiv Sena UBT, Sanjay Raut is angry

Mumbai: Operation Tiger has been successful. Shinde Sena has succeeded in forcing 6 MPs of Shiv Sena UBT to form another group, after which the rebellion has started again in UBT. The independent group has also been approved by the Lok Sabha Speaker. Now these 6 MPs can soon merge with Shiv Sena Shinde Party. After Operation Gaigar, Uddhav Thackeray group MP Sanjay Raut addressed a press conference and said that despite what Uddhav Thackeray did not do for these MPs, these people have acted dishonestly. This is dishonest. It is said that the rebel MPs are camped in Delhi and will merge with the Shinde group in the next two days. The operation in the state has been going on for the past several days and in June, a meeting of the India Alliance was also held in Delhi. In this meeting, Home Minister Amit Shah gave the green signal to Operation Tiger. The rebel MPs of the Thackeray group have been accommodated in a five-star hotel in Delhi. On Sunday, Uddhav Thackeray also held a meeting of his MPs in which five MPs attended the online meeting, due to which no one suspected them. This is the second biggest split in the Shiv Sena. After the rebellion of the Shiv Sena MPs, the Shiv Sena has become completely weakened. These rebel MPs include Sanjay Deshmukh, Ayut Mahal, Sanjay Jadhav, Parbhani, Sanjay Dina Patel, Mumbai, Nagesh Patil, Hingoli, Amarraje, Nimbalkar, Dhara Shiv. There is resentment in Shiv Sena after the rebellion of these MPs. Sanjay Raut is angry with them. He says that Uddhav Thackeray did so much for them but these people became dishonest.
Maharashtra
Muslim students deprived of government schemes… Only Hindu candidates are accepted for drone pilot training scheme: Raees Sheikh

Mumbai: Raising the issue of Muslim youth and students being deprived of the government’s ‘Amrit’ institute schemes, Samajwadi Party MLA from Bhiwandi East Raees Sheikh has said that applications are being accepted for the drone pilot training programme of the institute run by the state government’s Other Backward Classes Welfare Department, while online applications from Muslim candidates are not being accepted. In his letter to Minister Atal Seo and the Chief Executive Officer of Maharashtra Research, Advancement and Training (AMRUT) Institute, MLA Raees Sheikh said that the Amrit Institute has invited applications till June 30 for drone pilot training which is aimed at candidates from Economically Weaker Sections (EWS) of the open category. “However, when applicants try to fill the online form, they are required to provide information about their religion and caste. The portal offers caste options only for Hindu communities, which prevents Muslim applicants from successfully submitting their applications.” Sheikh said he had received several complaints regarding this issue. Pointing out that the Amrit Institute aims to serve the economically weaker sections in the open category, he said that as an autonomous government institution, the founding government resolution (August 22, 2019) of Amrit does not mention any specific religion. It aims to work for different communities in the open category. Therefore, restricting applications in this manner is against the rules, he claimed. The Maharashtra government has set up several institutions for different social groups, including Barati, Aarti, Sarathi, Mahajyoti, Marti, and Amrit. While each institution may focus on a specific target group, it can be limited to a certain extent. They also provide training opportunities to and benefits to other communities. Sheikh added that unemployment is currently a major concern for youth of all castes and religions across the state. He said, “The Amritsar should not interpret the rules in such a way that Muslim youth are deprived of skilling opportunities. Minister Atul Sivaji, who heads the Other Backward Bahujan Welfare Department, should ensure that Muslim youth are not excluded from these training programmes.”
-
Crime4 years agoClass 10 student jumps to death in Jaipur
-
Maharashtra2 years agoMumbai Local Train Update: Central Railway’s New Timetable Comes Into Effect; Check Full List Of Revised Timings & Stations
-
Maharashtra2 years agoMumbai To Go Toll-Free Tonight! Maharashtra Govt Announces Complete Toll Waiver For Light Motor Vehicles At All 5 Entry Points Of City
-
Maharashtra2 years agoFalse photo of Imtiaz Jaleel’s rally, exposing the fooling conspiracy
-
National News2 years agoMinistry of Railways rolls out Special Drive 4.0 with focus on digitisation, cleanliness, inclusiveness and grievance redressal
-
Maharashtra2 years agoMaharashtra Elections 2024: Mumbai Metro & BEST Services Extended Till Midnight On Voting Day
-
National News2 years agoJ&K: 4 Jawans Killed, 28 Injured After Bus Carrying BSF Personnel For Poll Duty Falls Into Gorge In Budgam; Terrifying Visuals Surface
-
Crime2 years agoBaba Siddique Murder: Mumbai Police Unable To Get Lawrence Bishnoi Custody Due To Home Ministry Order, Says Report
