Maharashtra
Sanjay Raut alleges Rs 400 crore corruption in PCMC school supplies procurement
Mumbai, July 10: Shiv Sena (UBT) leader and Rajya Sabha MP Sanjay Raut on Friday levelled serious allegations of a multi-crore corruption scandal within the Pimpri-Chinchwad Municipal Corporation (PCMC).
In an official letter addressed to Maharashtra Chief Minister Devendra Fadnavis dated July 9, 2026, Raut demanded immediate action against a senior cabinet minister and municipal officials for allegedly bypassing mandatory e-tendering processes and violating Supreme Court guidelines.
According to the letter, several local corporators from Pimpri-Chinchwad met with Raut to flag blatant illegalities in the procurement of school uniforms, sweaters, socks, raincoats, and school bags for primary and secondary school students. State regulations mandate that any civic procurement exceeding Rs 3 lakh must strictly go through an “e-tender” system. However, a multi-crore contract was directly awarded to Solapur-based Jagdamba Readymade Dresses Sahakari Sanstha without any competitive bidding, alleged Raut.
Raut said that the matter had previously reached the Supreme Court, which had capped the procurement rate of the school kits at Rs 239 per unit. Instead, the PCMC administration allegedly awarded the contract at an inflated rate of Rs 814 per unit—resulting in a staggering overpayment of Rs 575 per kit funded by taxpayers. Raut estimated the total scale of the scam to be approximately Rs 400 crore.
He did not mince words, directly accusing a senior minister within the state cabinet of using political muscle to push the deal through. “A senior minister from your cabinet pressured the Municipal Commissioner to illegally award this contract to the firm without any tender process,” Raut wrote, invoking Prime Minister Narendra Modi’s famous anti-corruption slogan, ‘Na khaunga, na khane dunga’ (“I will neither take bribes, nor allow anyone else to take them).
Raut further alleged that this pressure was driven by financial kickbacks rather than public interest, claiming that a massive cut of Rs 50 to Rs 55 crore allegedly reached the concerned ministers. He described corruption targeting school supplies for children as “deeply shameful.”
Concluding his letter, Raut urged CM Fadnavis to order an immediate inquiry and take strict action against the complicit minister and the PCMC administration. He confirmed that a complete set of documentary evidence detailing the alleged corrupt practices has been formally submitted to the Chief Minister’s Office for review.
Maharashtra
Questions Raised by Mumbai MLAs Drop 72% in 15th Assembly, Praja Foundation Report Reveals

MUMBAI, August 25, 2026: Legislative participation among Mumbai’s elected representatives has witnessed a sharp decline, with total questions raised in the Maharashtra Legislative Assembly dropping by 72% compared to the 12th Assembly, according to the ‘Mumbai MLA Report Card 2026’ released by Praja Foundation.
The report evaluated the performance of 33 Mumbai MLAs across the Winter 2024 and Monsoon 2025 sessions based on session attendance, participation, quality of questions raised, and overall constitutional duties. Out of 33 MLAs, only three scored above 80%, with Indian National Congress representatives securing all top three positions.
Top Performing MLAs
Rank 1: Amin Patel (Congress) — Score: 82.89
Rank 2: Aslam Shaikh (Congress) — Score: 80.58
Rank 3: Jyoti Gaikwad (Congress) — Score: 80.30
Key Report Findings
Plunge in Legislative Inquiries: MLAs asked only 2,213 questions in the 15th Assembly (Winter 2024 – Monsoon 2025), down significantly from 7,955 questions in the 12th Assembly (Winter 2009 – Monsoon 2010).
Decline in Question Quality: The quality score of questions asked dropped from an average of 50% in the 12th Assembly to 33% in the 15th Assembly.
Fewer Working Days: In its first year, the 15th Assembly met for only 40 working days, compared to 47 days in the 12th Assembly and 50 days in the 13th Assembly.
Stagnant Overall Scores: The overall average performance score of legislators fell from 61 in the 12th Assembly to 54 in the 14th Assembly, before slightly recovering to 55 in the 15th Assembly.
Aging Representatives: The average age of Mumbai MLAs has progressively increased over time, moving from 52 years (12th Assembly) and 51 years (13th Assembly) to 53 years (14th Assembly) and now 57 years in the 15th Assembly.
Concerns Over Democratic Accountability
Addressing the findings, Milind Mhaske, CEO of Praja Foundation, stated that performance metrics reflect whether citizens’ concerns are reaching the house floor. While top performers demonstrated strong engagement, the overall stagnating scores highlight significant gaps in representation.
Asif Khan, Manager at Praja Foundation, warned that shorter session durations and fewer quality questions deprive citizens of a critical mechanism to hold the government accountable.
Maharashtra
Mumbai: Youth arrested for throwing an egg at the Mazgaon Ganpati procession.

Police have claimed to have arrested a fanatic youth who threw eggs during a Ganpati procession in Mazgaon, Mumbai. On the night of August 23, a procession of the Raja of Mazgaon was taken out in Mumbai. During this time, a youth who was going to the same building for egg delivery was disturbed by the dust and smoke of crackers during the procession and in anger he threw an egg at the Ganpati idol, after which the situation became tense. However, the police identified the accused with the help of CCTV and he was arrested today. He has been identified as Danish Sher Khan, 22. The police traced the accused within 36 hours. Now the situation is tense, but peace has been restored. Just before Eid Milad-un-Nabi, the police arrested the anti-social Danish and started the investigation. In the initial investigation, the police have found that the accused had committed this act in anger. The accused was carrying an online order. Meanwhile, due to the crowd in the procession with him, his eyes were hurt by the smoke and dust of the crackers, which caused him to lose his temper. The egg I had brought for delivery was thrown at the Ganpati procession, after which the situation became tense and the police resolved the matter. This action was taken by DCP Jayant Meena on the instructions of Mumbai Police Commissioner Devin Bharti.
Maharashtra
Versova-Bandra Sea Link gets a 1,421-day extension — where is the penalty?

Mumbai: Information provided by the Maharashtra State Road Development Corporation (MSRDC) under the Right to Information (RTI) Act has revealed significant delays in Mumbai’s ambitious Versova Samudra Bandra Sea Link (VBSLP) project. The project’s start date was June 24, 2019, and under the original contract, it was scheduled to be completed by June 21, 2024. However, due to various reasons, the project has been extended by a total of 1,421 days in four phases, despite which the final revised completion date was pushed forward, not to May 2, 2024, but to May 17. No penalty has been imposed on the contractor, Webuild-Apco JV.
According to information provided by MSRDC in response to an RTI application filed by Anil Gilgli, the first extension of 250 days was granted on June 23, 2020. The main reason was non-availability of land required for the casting yard. Subsequently, on September 14, 2020, an additional extension of 180 days was granted due to restrictions and work disruptions due to the COVID-19 pandemic. Later, on February 10, 2022, an extension of 483 days was granted due to restructuring or changes within the EPC contractors’ joint venture (JV). Finally, on January 19, 2024, a further extension of 508 days was granted due to changes in the scope of work and additional works. The total duration of these four extensions is 1,421 days, with the final date of completion of the project set at May 17, 2028. According to the MSRDC letter dated June 23, 2020, the contractor had sought an extension of about 311 days for the period from April 2020 to April 2020. The reasons for the delay during this period include various incidents as well as the COVID-19 pandemic. Subsequently, revised work phases and timelines were established for the project. Meanwhile, the MSRDC letter dated January 19, 2024 mentions further extension based on changes in the scope of work and revision of work phases.
A serious question arises as to why no punitive action has been taken against the contractor Webuild-Apco JV for the delay despite repeated extensions to the project. RTI activist and senior journalist Anil Gilgali said that the financial burden of delay in this important project, which was run with public money, may ultimately fall on the government exchequer and the common people. Therefore, instead of simply giving relief to Webuild-Apco JV by way of extension of time, the penalty provisions stipulated in the contract should be strictly enforced.
“The Versova-Bandra Sea Link project has been given an extension of a total of 1,421 days. The original completion date was June 21, 2024, while the last date has now been extended to May 17, 2028. The delay in the project is resulting in wastage of both public funds and time. Therefore, by simply stating the reason, the reason is given. Anil Galgali demanded that damages (LD)—penalties for compensation for losses—should be immediately imposed on the contractor, Webuild-Apco JV and recovered as per the provisions of the contract. Galgali added, “An extension does not mean allowing the Webuild-Apco JV contractor to delay the work. While some reasons for the delay may be acceptable, the responsibilities and penalty clauses stipulated in the contract must be implemented. It is a matter of serious concern that the final deadline for this project, which was set on June 2, 2019—has now been extended to May 17, 2028. Therefore, MSRDC should publicly disclose clear details about the reasons for each extension, the party responsible for the delay, the additional financial burden resulting from it, and whether the damages have been averted.
The Versova-Bandra Sea Link is a key project for Mumbai’s traffic infrastructure. However, the project timeline continues to be extended due to continuous delays in the work. Consequently, the Maharashtra State Road Development Corporation (MSRDC) should clearly identify the reasons and accountability for these delays and recover penalty from the Webuild-Apco JV contractor for any delays attributable to them, as per the contract. Additionally, RTI activist Anil Gilgali has demanded steps to ensure that the extended project period does not impose additional financial burden on the government exchequer.
-
Crime4 years agoClass 10 student jumps to death in Jaipur
-
Maharashtra2 years agoMumbai Local Train Update: Central Railway’s New Timetable Comes Into Effect; Check Full List Of Revised Timings & Stations
-
Maharashtra2 years agoMumbai To Go Toll-Free Tonight! Maharashtra Govt Announces Complete Toll Waiver For Light Motor Vehicles At All 5 Entry Points Of City
-
Maharashtra2 years agoFalse photo of Imtiaz Jaleel’s rally, exposing the fooling conspiracy
-
National News2 years agoMinistry of Railways rolls out Special Drive 4.0 with focus on digitisation, cleanliness, inclusiveness and grievance redressal
-
Maharashtra2 years agoMaharashtra Elections 2024: Mumbai Metro & BEST Services Extended Till Midnight On Voting Day
-
National News2 years agoJ&K: 4 Jawans Killed, 28 Injured After Bus Carrying BSF Personnel For Poll Duty Falls Into Gorge In Budgam; Terrifying Visuals Surface
-
Crime2 years agoBaba Siddique Murder: Mumbai Police Unable To Get Lawrence Bishnoi Custody Due To Home Ministry Order, Says Report
